Prioritizing Stakeholders in Project Management: Application of the Multicritery Hierarchy Analysis Method - AHP

Authors

DOI:

https://doi.org/10.26668/businessreview/2021.v6i1.195

Keywords:

Stakeholders, Project management, Multicriteria Analysis, Stakeholder Theory

Abstract

Objective of the study: this article aims to propose a hierarchy of criteria for the classification of stakeholders in Information Technology (IT) projects.

Methodology: The prioritization method used is the AHP (Analytic Hierarchy Process) methodology in order to propose a ranking based on predefined criteria that may have its relevance adjusted according to the project's characteristics. Factors related to the attributes of power, legitimacy, urgency, interest, influence and impact of stakeholders in the projects were considered, investigating a sample of 53 project managers.

Originality / Relevance: The use of the stakeholder approach and the AHP method provide a tool for prioritizing stakeholders in IT projects.

Main results: In the evaluation of criteria that need more attention in management, it was found that stakeholders with Power, Legitimacy and Influence are the ones that usually demand more attention from project managers, thus leaving the criteria of Urgency, Interest and Impact as lower relevance.

Methodological contributions: a method is presented that can be used and suitable for each project according to its environment and characteristics, making the classification of stakeholders to be customized and based on comparisons and not on perceptions.

Contributions to management: refers to the improvement of the ability to classify stakeholders in IT projects, presenting a proposal to prioritize actions with the most critical stakeholders, suggesting a method for ordering that will facilitate the performance of the management team in cases of many people with a high probability of impacting or being impacted by the project.

Downloads

Download data is not yet available.

Author Biographies

Keysa Manuela Cunha Mascena, University of Fortaleza - UNIFOR

Doutora em Administração pela Faculdade de Economia, Administração, Contabilidade e Atuária da Universidade de São Paulo - FEA/USP, São Paulo, (Brasil). Professora da Universidade de Fortaleza – Unifora, Ceará, (Brasil).

Fabricio Stocker, University of Sao Paulo

Faculdade de Economia, Administração e Contabilidade FEA-USP

References

Archibald, R. D. (2005) Os propósitos e Métodos da Categorização Prática de Projeto. Revista Mundo PM. São Paulo, n. 05, p. 28-38, Out/Nov.

Elias, A. A., Cavana, R. Y. & Jackson, L. S. (2002). Stakeholder analysis for R&D project management. R&D Management, v.32, n.4, p.301-310.

Gonçalves, V; Campos, C. (2016). HCMBOK – Human Change Managment Body of Knowledge, 1. ed. CRC Press.

Guedes, A.D. L.; Mendes, S. P. (2005). Gerenciamento de stakeholders: uma contribuição à otimização do papel dos stakeholders, da gerência de conversas e do ciclo de coordenação de ações em projetos de TI. Mundo Project Management, Rio de Janeiro: Editora Mundo, ano 1, n.5, p. 66-73, out./nov.

Freeman, R.E. (1984). Strategic management: a stakeholder approach. Boston: Pitman.

Freeman, R. E. (2017). The new story of business: Towards a more responsible capitalism. Business and Society Review, 122(3), 449-465.

Friedman, A. L. & Miles, S. (2006). Stakeholders: Theory and Practice. New York: Oxford University Press.

Huang, I. B., Keisler, J., & Linkov, I. (2011). Multi-criteria decision analysis in environmental sciences: Ten years of applications and trends. Science of the Total Environment, 409(19), 3578-3594.

Jugdev, K.; Müller, R. A (2005). retrospective look at our evolving understanding of project success. Project Management Institute.

Kerzner, H. (2010). Gestão de Projetos: as melhores práticas. 2. ed. Porto Alegre: Bookman.

Mascena, K. M. C.; Kim, J. Fischmann, A. A.; Corrêa, H. (2015). Priorização de Stakeholders: Contribuição dos estudos teóricos e empíricos. Revista de Administração da UFSM, v. 8, p. 42-59.

Mascena, K. M. C. D., Fischmann, A. A., & Boaventura, J. M. G. (2018). Stakeholder Prioritization in Brazilian Companies Disclosing GRI Reports. BBR. Brazilian Business Review, 15(1), 17-32.

Mitchell, R.K., Agle, B.R. & Wood, D.J. (1997). Toward a theory of stakeholder identification and salience: defining the principle of who and what really counts. Academy of Management Review, v.22, n.4, p.853-886.

PMBOK. (2017). Guia PMBOK®: Um Guia para o Conjunto de Conhecimentos em Gerenciamento de Projetos. PMI - Project Management Institute. 6. ed. Pennsylvania: PMI, 2017.

PMBOK. (2013). Guia PMBOK®: Um Guia para o Conjunto de Conhecimentos em Gerenciamento de Projetos. PMI - Project Management Institute. 5. ed. Pennsylvania: PMI, 2013.

Saaty, T. L. (2006). Rank from comparisons and from ratings in the analytic hierarchy/network processes. European Journal of Operational Research, 168(2), 557-570.

Saaty, T. L. (2008). Decision-making with the analytic hierarchy process. International Journal of Services Sciences, 1(1), 83-98.

Sarturi, G., Mascena, K. M. C., Boaventura, J. M. G., & Pilli, L. E. (2018). Relação entre Saliência de Stakeholders e Desempenho Financeiro. Revista Contabilidade, Gestão e Governança, 21(2), 214-230.

Stocker, F., Arruda, M. P., Mascena, K. M. C. & Boaventura, J.M.G. (2020). Stakeholder engagement in sustainability reporting: a classification model. Corporate Social Responsibility and Environmental Management. 1–10.

Stocker, F., Villar, E. G., Roglio, K. de D., & Abib, G. (2018). Dismissal: Important criteria in managerial decision-making. RAE-Revista de Administração de Empresas, 58(2), 116-129.

Stocker, F., Mascena, K., Azevedo, A., & Boaventura, J. (2019). Teoria de Redes de Influências de Stakeholders: uma abordagem revisitada. Cadernos EBAPE.BR, 17(SI), 673-688.

Stocker, F., & de Mascena, K. M. C. (2019). Orientação e gestão para stakeholders no processo de decisão organizacional. Revista de Gestão e Secretariado, 10(1), 167-191.

Wood, D. J., Mitchell, R. K., Agle, B. R., & Bryan, L. M. (2018). Stakeholder Identification and Salience After 20 Years: Progress, Problems, and Prospects. Business & Society. 1-50.

	Stakeholders, Project management, Multicriteria Analysis, Stakeholder Theory

Published

2021-01-03

How to Cite

Mascena, K. M. C., Santos, F. V., & Stocker, F. (2021). Prioritizing Stakeholders in Project Management: Application of the Multicritery Hierarchy Analysis Method - AHP. International Journal of Professional Business Review, 6(1), e195. https://doi.org/10.26668/businessreview/2021.v6i1.195